A rebuild runs on the general contractor's sequence. Framing, rough plumbing and electrical, insulation, drywall, then cabinets, then counters. Cabinets sit in the middle of that chain, so a late cabinet order stalls the countertop fabricator, the plumber's finish visit and the final inspection behind it.
That's why we ask for the builder's schedule early and a named contact on site. Our design and install process needs the rough-in positions locked before the boxes are built. A sink drain stubbed two inches off center is cheap to move in an open wall. After drywall, it's a patch, a repaint and a lost day for three trades.
If your builder already has a cabinet package
Most builders include a cabinet allowance. You can take it, upgrade within it, or carve the kitchen out of the contract and bring in your own cabinet contractor. That last route works only if the builder agrees in writing to rough in to our drawings and schedule counters after our install. Settle it before framing, and plan mudroom lockers or a pantry wall while the studs are still open.